Week Ending 2026-05-24
Digest generated at 2026-05-22T18:34:58.895Z
SUBMISSIONS
7
(0)
RED
0
(-3)
Compared to 2026-05-17
No RED or YELLOW deteriorations this week.
Convergint install is currently held due to unresolved cabling responsibility between Convergint and Crowe, with confirmation needed on ownership and completion path. Kristie's return is expected to help escalate vendor coordination. Mon...
Current activity is focused on confirming data readiness and receiving final dataset transfer and curation outputs from stakeholders. Follow-ups are ongoing regarding data culling progress and NAS disposition planning. ISP coordination i...
Putting this in yellow as we have not heard back from the agency yet regarding the validation document for the migration. Ed from Orch was able to change the Forsman users' Maconomy login to 72andSunny which is one workstream accomplishe...
Putting this one in Yellow as we have a critical deadline happening next week for the device login username change. Migration is almost completed and we are ready to switch them fully to assembly, one blocker is device replacement. For n...
Stagwell HR Recruitment: - Initial version of SDD sent over to Nick and Saif. - Necessary requirements gathered and identified. - Initial POC demo for the prehire integration presented to Nick/Saif - Changes made to the existing scenario...
72 and Sunny Dashboards Two Week Sprint - Monday Client Working Session - Requirements Gathering - Made progress on 4 dashboards Tuesday Client Working Session - Proceed with remaining dashboards & Project Scope Technical Doc send to Age...
8 dashboards on track for 05/21. Tony set to complete the new dataset by Tuesday. Arun to validate the sample shared today by Monday, with Manoj preparing tables so Ravi can start creating the dashboards. UAT plan to be created by Monday...
ACIIFOTECH Offboarding Workiva Kick Off Call, Project start next Monday (Highly important in our team) Maconomy testing for failed automation, resolution before the scheduled Maconomy upgrade IC Allocation Phase 2 is ongoing for development
Biggest focus this week is the Targeted Victory Discovery.
Colle Mcvoy Migration Testing - Internal testing is complete and successful Core functionality validated: - Successful device migrations - Users can authenticate and connect to internal Wi-Fi Deployment Decision - No live migration meeti...
16 more items not shown.
No persistent risks detected.
Read-only source submissions for week ending 2026-05-24.
Submitted 2026-05-21T22:24:44.275Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Orchestration & Automation
Blockers
Leadership Context
P2
Networking Dev Ops
Blockers
Leadership Context
P3
Networking Dev Ops
Blockers
Leadership Context
Submitted 2026-05-22T18:08:57.513Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Stagwell CSC Program
P2
Stagwell CSC Program
P3
Stagwell CSC Program
Submitted 2026-05-22T17:03:59.552Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Orchestration & Automation
Blockers
P2
Orchestration & Automation
Blockers
P3
Orchestration & Automation
Blockers
Submitted 2026-05-22T21:00:45.917Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Communication & Collaboration
Blockers
P2
Communication & Collaboration
P3
Orchestration & Automation
Submitted 2026-05-22T22:27:10.990Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
Leadership Support
Reason
DECISION_REQUIRED
Timing
THIS_WEEK
Notes
Go‑Live Approach Discussion Needed for Harris Poll. >Consideration of phased or partial rollout, including: -Starting with project management functionality only (Workfront) -Delaying full Maconomy integration if needed > Full-blown go-live roll out on July 1st
P1
Stagwell CSC Program
Blockers
P2
Stagwell CSC Program
Blockers
P3
Stagwell CSC Program
Blockers
Leadership Context
Submitted 2026-05-20T18:55:39.143Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
Leadership Support
Reason
DECISION_REQUIRED
Timing
THIS_WEEK
Notes
Meeting today 5/20 w/Dayne and Paul on Process sign off for UAT in order to disseminate/align on resource availability for CoE and key partners.
P1
Stagwell CSC Program
Blockers
P2
Stagwell CSC Program
P3
Stagwell CSC Program
Submitted 2026-05-22T19:29:07.541Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Unassigned
P2
Unassigned
P3
Unassigned
Complete archive list for direct week access.
| Week Ending | Generated (UTC) | Action |
|---|---|---|
| 2026-06-07 | 2026-06-10T17:51:50.713Z | Open Submission Archive |
| 2026-05-24 | 2026-05-22T18:34:58.895Z | Viewing |
| 2026-05-17 | 2026-05-22T18:35:51.576Z | Open Submission Archive |
| 2026-05-10 | 2026-05-22T18:35:19.325Z | Open Submission Archive |
| 2026-05-03 | 2026-05-08T17:20:00.855Z | Open Submission Archive |
| 2026-04-26 | 2026-04-27T21:55:44.672Z | Open Submission Archive |
| 2026-04-19 | 2026-04-29T17:58:27.785Z | Open Submission Archive |
| 2026-04-12 | 2026-04-13T13:22:30.934Z | Open Submission Archive |
| 2026-04-05 | 2026-04-06T14:23:12.310Z | Open Submission Archive |
| 2026-03-29 | 2026-03-30T13:15:16.542Z | Open Submission Archive |
| 2026-03-22 | 2026-03-17T22:25:47.706Z | Open Submission Archive |
| 2026-03-15 | 2026-03-16T22:10:16.138Z | Open Submission Archive |
| 2026-03-08 | 2026-03-05T22:37:17.288Z | Open Submission Archive |
| 2026-03-01 | 2026-03-05T22:37:20.021Z | Open Submission Archive |
| 2026-02-22 | 2026-02-25T00:08:55.076Z | Open Submission Archive |