History

Week Ending 2026-06-07

Digest generated at 2026-06-10T17:51:50.713Z

SUBMISSIONS

8

(+3)

RED

1

(+1)

Week-over-Week Signals

Compared to 2026-05-31

Deteriorations (0)

No RED or YELLOW deteriorations this week.

New Signals (6)

YELLOW

Endpoint migration is nearing completion, with only a small number of MDM profile approvals remaining. User comms was sent and the next comms is planned for Monday, ahead of the upcoming all-hands. Discovery identified a separate M365/Sh...

YELLOW

Harris Poll CSC implementation progressing with UAT largely completed. Functionally on track for go-live, but operational risk remains due to unresolved ownership, process dependencies, and system limitations requiring interim workaround...

YELLOW

I have already raised and followed up this week for the validation document from the agency. They confirmed that they are working on it and will give me feedback next week. Will check again early next week so we can move to the initial m...

YELLOW

ISP follow-up remains active through business partner contacts. Data/NAS discussions continue with key stakeholders. Restoration obligations have been communicated, and additional escalation paths have been established to drive action. C...

YELLOW

Stagwell HR/Recruitment: • Integration foundation live and stable (sandbox) with real-time data flowing into Workfront • Partial automation achieved (candidate creation + data ingestion working) • Full end-to-end automation in progress (...

1 more items not shown.

Resolved (15)
GREEN

• Conducted the first weekly project meeting • Presented the proposed approach for tracking project progress • Recommended automation to generate tickets from a shared mailbox • Aligned expectations on the creation of a weekly slide deck...

GREEN

• The Workfront board has been set up and is now ready for use • Granular tasks have been defined, including estimated durations • The project remains in the planning phase ahead of formal kickoff • A follow-up meeting is scheduled next...

GREEN

• Workfront board is now ready for use • Granular tasks have been listed with estimated durations • Project is currently in the planning stage prior to kickoff • Follow-up meeting scheduled next week to define the approach for pre-projec...

GREEN

Bizapps Migration - Still pending on documentation review so we can proceed with customization EUC | Okta & Hive User Setup Process Refresher Session - 6/4

YELLOW

Comcast internet has been installed successfully, and Lumen equipment is present in the building. However, Lumen still requires an extension installation to the 4th floor, which has not yet been scheduled. Monoprice equipment has been or...

10 more items not shown.

Persistent Risks

No persistent risks detected.

Weekly Submission Archive

Read-only source submissions for week ending 2026-06-07.

Arriana Pabalate

Submitted 2026-06-05T19:14:31.914Z

R 0Y 2G 1Blockers
3 priority items

Priorities

  • P1 PRJ-008 Team - Jetfuel Onboarding
  • P2 PRJ-035 INK - Miami Office Decommission
  • P3 PRJ-025 Stagwell Global - Singapore Office Hub

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-008 Team - Jetfuel Onboarding

Orchestration & Automation

YELLOW

Endpoint migration is nearing completion, with only a small number of MDM profile approvals remaining. User comms was sent and the next comms is planned for Monday, ahead of the upcoming all-hands. Discovery identified a separate M365/SharePoint tenant; initial assessment and domain usage review are underway. Three new Macs have been ordered and enrolled in DEP/ABM, with device deployment planning in progress. SentinelOne pilot remains active and awaiting the next checkpoint.

Blockers

Custom domain association within the separate M365 tenant may block domain addition to the target environment if not addressed before cutover. Domain usage has been confirmed in the separate SharePoint environment; retention and migration requirements are still being evaluated. Remaining MDM profile approvals require closure, though they are not currently impacting timeline.

Leadership Context

Migration activities are substantially complete, and focus is shifting toward cutover readiness and risk mitigation. Discovery of the secondary M365 tenant introduced a new dependency that could impact final domain migration planning. DNS access coverage and administrative permissions are being reviewed to reduce single-person dependencies during cutover.

P2

PRJ-035 INK - Miami Office Decommission

Networking Dev Ops

YELLOW

ISP follow-up remains active through business partner contacts. Data/NAS discussions continue with key stakeholders. Restoration obligations have been communicated, and additional escalation paths have been established to drive action. Coordination continues between IT and facilities stakeholders regarding site decommissioning responsibilities.

Blockers

ISP service status remains unresolved pending vendor response through the business partner. Data/NAS discussions are delayed due to difficulty scheduling time with key stakeholders. Ownership of site decommissioning activities remains unclear, with limited engagement from parties responsible for non-IT assets. A previously scheduled walkthrough was canceled and has not yet been rescheduled. Significant non-IT equipment, including studio assets, falls outside IT scope and requires separate coordination.

Leadership Context

Project progress is increasingly dependent on stakeholder engagement rather than technical execution. Clear ownership and accountability for decommissioning activities may require leadership intervention. Delays in communication and coordination could impact facility exit timelines.

P3

PRJ-025 Stagwell Global - Singapore Office Hub

Networking Dev Ops

GREEN

Site is operational and substantially complete. Loaner firewalls are currently in production while configuration migration to permanent hardware is underway. Troubleshooting continues on Logitech Teams devices experiencing call-related disconnects. Initial testing suggests the issue may not occur on wireless connections. Vendor support case has been opened, and additional testing results are being collected. Network equipment quote has been received, and procurement planning is underway.

Blockers

Firewall configuration migration to permanent devices is still outstanding. Logitech Teams devices continue to experience disconnects approximately 30 minutes into calls, affecting meeting reliability. Root cause has not yet been confirmed despite firmware updates and network testing. Procurement approval is pending for additional network hardware required at the site.

Leadership Context

Core site deployment is effectively complete, with remaining work focused on stabilization and optimization. Vendor engagement is active for the conferencing device issue, with a potential temporary wireless workaround available. Hardware procurement approval will be required to complete remaining network improvements.

Casey Younggren

Submitted 2026-06-08T11:17:32.371Z

R 0Y 0G 3
3 priority items

Priorities

  • P1 PRJ-011 AI Enablement
  • P2 PRJ-010 CSC Agency Implementation
  • P3 PRJ-014 Global Projects Team Coordination

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-011 AI Enablement

Stagwell CSC Program

GREEN

Stagwell Corp Sessions - Did a lot of coordination with Paul on this last week, holds sent. Stagwell HR Sessions - Dates in progress. Veritas - Sessions in progress. Colle Mc Voy - Sessions tbd, but dates given. Hunter - Sessions complete for Copilot, working on Adobe sessions. Allison - had a coordination call last week with Antonio, sessions tbd. Corp Finance - Kickoff and coordination call complete, sessions tbd.

P2

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

GREEN

INK and Locaria discovery dates set - INK will be the week of July 6, Locaria week of July 13. Targeted Victory is off pause and will begin sol. design. Coordinated agencies and slotted them in priority order with Paul, connected with Priya on them. Working on agency profiles with Priya's template. Met with Antonio to talk about Allison's discovery - they will need another session (also doing w AI enablement) Team, Anomaly, F&B are in good standing. UNR still needs to complete solution design.

P3

PRJ-014 Global Projects Team Coordination

Stagwell CSC Program

GREEN

Migrating my notes to the daily core folder. Adobe items: governance accelerator workshop coordinating, Maturity assessment got that out, had meetings for CFO dashboards, non labor resource reporting, and sandbox environment, and client level reporting

Giuseppe Enriquez

Submitted 2026-06-04T21:27:35.143Z

R 0Y 0G 3
3 priority items

Priorities

  • P1 PRJ-041 Allison (Sloan-SKDK) - UKG Automation
  • P2 PRJ-042 72andSunny (Forsman/BMD) - UKG Automation
  • P3 PRJ-021 Consulum Onboarding

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-041 Allison (Sloan-SKDK) - UKG Automation

Orchestration & Automation

GREEN

Wrapping up onboarding/offboarding setup for Sloan, with only a few remaining items: - Finalizing user type assignments - Cleaning up master data between UKG and Okta Action Items: Lisa → Update alternate titles in UKG Vanessa → Validate titles with Sloan EA (Amelia) Orch → Validate Okta group rules before syncing Orch → Investigate early Okta notifications Orch → Review audit workbook (titles & departments tabs) Going live tomorrow

P2

PRJ-042 72andSunny (Forsman/BMD) - UKG Automation

Orchestration & Automation

GREEN

Automation is already live. Wrapping this up by EOW. Remaining work to be finished by Friday EOD: - BMD automation logic - Department normalization - Notification list cleanup: Update distribution lists for notifications

P3

PRJ-021 Consulum Onboarding

Orchestration & Automation

GREEN

Build & Environment Migration environment is mostly complete: - 30 policies successfully migrated - Core configuration profiles identified and being reviewed Remaining work: - Validate configuration profiles (including custom XMLs) - Align settings with Stagwell standards Build testing will begin after Paul returns from PTO Device Landscape Heavy Apple ecosystem usage: - MacOS devices (150–160 active machines) - iOS devices with 200+ apps deployed (100+ per user max) - Minimal iPad usage (only 1 active device) - Regional distribution across locations (Dubai, Bahrain, London, etc.) Testing Strategy Phase 1: Internal Testing - Use controlled test machines (London initially) Phase 2: User Pilot Testing Target: - 2–3 users per location - Include IT-savvy users and regional representatives Coverage: - Dubai, Bahrain, London, etc. Objective: - Validate real-world usage: - Login flows - Apps - Security - Productivity Requested Ash and Nesty to provide a list of users for pilot testing next week.

Givan Turla

Submitted 2026-06-05T19:39:24.503Z

R 0Y 1G 2
3 priority items

Priorities

  • P1 PRJ-029 72andSunny - Forsman & BMD - Merge/Rebrand
  • P2 PRJ-023 ADK Merge to Assembly
  • P3 PRJ-040 Crispin M365 to Google Migration

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-029 72andSunny - Forsman & BMD - Merge/Rebrand

Communication & Collaboration

YELLOW

I have already raised and followed up this week for the validation document from the agency. They confirmed that they are working on it and will give me feedback next week. Will check again early next week so we can move to the initial migration phase. We also built out a core app for BMD Google and provisioned them google cloud identities as part of BMD's move from 365 to Google.

P2

PRJ-023 ADK Merge to Assembly

Communication & Collaboration

GREEN

Successfully went live with ADK Thailand's device domain change. All users from ADK -TH has been change to their new Assembly subdomain whilst awaiting the device refresh from Craig. Next steps for next week is to do a device domain migration for one user from ADK Australia so we can proceed with fully transitioning them over together with ADK Hongkong.

P3

PRJ-040 Crispin M365 to Google Migration

Communication & Collaboration

GREEN

Successfully went live with Wave 2 last Monday. We are currently in discussion for prepping Wave 3. As per our agency contact they are prepping the site on their end and finishing some work. Once done, we can proceed with the initial sync.

John Louie

Submitted 2026-06-05T22:08:42.997Z

R 0Y 0G 3Blockers
3 priority items

Priorities

  • P1 PRJ-037 IT Security: Q2 IT Security: Core Stagwell LLC - PowerDMARC Domains Master List
  • P2 PRJ-038 IT Security: OER 2026
  • P3 PRJ-043 IT Security: CMMC Project

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-037 IT Security: Q2 IT Security: Core Stagwell LLC - PowerDMARC Domains Master List

Security & Compliance

GREEN

• DMARC Hosted Setup / Audit – In progress at 50.64% completion. • SPF Hosted Record – In progress at 9.25% completion. • DMARC Quarantine – Initiated with 0.40% completion. • DMARC Reject Enforcement – Scheduled for the next phase; no progress recorded yet. • Proofpoint SPF / DMARC / DKIM Control Review – Planned and pending execution. • PowerDMARC Alerting – Planned and pending implementation. Overall Status: Project activities remain focused on the DMARC configuration and SPF record implementation phases. DMARC quarantine activities have commenced, while reject enforcement, control review, and alerting components are scheduled for subsequent execution phases. Progress is tracking against the planned implementation roadmap.

Blockers

None.

Leadership Context

To improve execution, focus and delivery predictability, a targeted deployment approach has been requested. By next week, the team is expected to provide a prioritized list of focus agencies aligned to specific timelines, enabling a structured rollout plan rather than deploying resources on an ad hoc basis. This will support better planning, resource allocation, and progress tracking.

P2

PRJ-038 IT Security: OER 2026

Security & Compliance

GREEN

Granular project tasks have been loaded into Workfront to support detailed tracking and execution. Coordination with Amy is ongoing to confirm target dates, with the project kickoff currently estimated for June 20. In addition, a request has been made for a comprehensive list of documents that will need to be obtained from the respective system owners, ensuring all required artifacts and dependencies are identified and tracked.

Blockers

None

Leadership Context

To establish clear execution timelines and improve project visibility, detailed tasks have been structured within Workfront and target dates are being aligned with key stakeholders. Additionally, a request has been made to identify all documentation requirements from the respective system owners upfront. This approach is intended to provide early visibility into dependencies, ensure timely document collection, and enable proactive tracking.

P3

PRJ-043 IT Security: CMMC Project

Security & Compliance

GREEN

I am continuously coordinating with Omar regarding the granular tasks required for the project. He initially committed to share the details by June 4, 2026; however, the scheduled meeting with Shannon and the relevant representative was moved to Monday. Following that discussion, Omar has confirmed that he will provide the required granular task breakdown.

Blockers

None.

Leadership Context

Continuous coordination is ongoing with Omar to finalize the granular task breakdown required for project execution. While an initial commitment was made to provide the details by June 4, 2026, this was deferred due to the rescheduling of a key discussion with Shannon and the relevant stakeholder, now set for Monday. Omar has confirmed that the granular task details will be shared immediately after that meeting, ensuring alignment with stakeholders and enabling progression of the project plan.

Kirsten Margarette Lagura

Submitted 2026-06-05T23:51:02.250Z

R 1Y 0G 2Blockers
3 priority items

Priorities

  • P1 PRJ-010 CSC Agency Implementation
  • P2 PRJ-019 CSC Systems Integration
  • P3 PRJ-010 CSC Agency Implementation

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

RED

The 72NS UAT Kick-off is now moved to Tuesday, Jun-9 as requested by the testers. While waiting, the engineers continued to meet with Tony to finalize the dataset. Milda was available throughout to respond to questions.

Blockers

Engineers always found something wrong with the dataset causing them to go back and forth with Tony.

P2

PRJ-019 CSC Systems Integration

Stagwell CSC Program

GREEN

The EAC automation will resume next week. This week - Adobe, PowerBI and CSC teams met to align on what’s been worked on. When Dayne gets back, there’s an open question on the scope of the data that needs to be clarified. Next meeting is on June 9 with the larger group.

Blockers

Scope clarity

P3

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

GREEN

Harris X went live but their two necessary custom integrations are still pending. Daniel and i took initiative to seek out next steps to unblock the access blocker the Odin team is experiencing. We will meet with Lauren to finalize SOP before proceeding with technical sessions.

Krizzia Vic Amparo

Submitted 2026-06-05T21:50:58.096Z

R 0Y 2G 1Blockers
3 priority items

Priorities

  • P1 PRJ-010 CSC Agency Implementation
  • P2 PRJ-010 CSC Agency Implementation
  • P3 PRJ-010 CSC Agency Implementation

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

GREEN

Doner Agency: Doner Asset Migration (Xinet/Box → AEM): Stagwell Pilot migration completed: 99 assets successfully migrated to AEM • Metadata applied to 80 assets based on the source spreadsheet • 19 assets pending metadata due to filename discrepancies vs. spreadsheet • Next step: Client validation required to resolve mismatches. Alignment call scheduled next week to confirm updates and proceed Fusion AI–Driven Intake Automation: • UAT completed; Doner sign-off approved • Scenario successfully deployed to production Next Steps: Finalize documentation and complete hypercare through June 15 Project Boards: Initiative re-engaged; Excel mock-up of Workfront project template fields in progress (owner: Chelsey) Next Step: Use completed mock-up to kick off detailed discussions and move initiative forward.

Blockers

n/a

Leadership Context

n/a

P2

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

YELLOW

Stagwell HR/Recruitment: • Integration foundation live and stable (sandbox) with real-time data flowing into Workfront • Partial automation achieved (candidate creation + data ingestion working) • Full end-to-end automation in progress (limited by trigger constraints from iCIMS) Next Steps • Call with Recruitment/iCIMS next week to finalize trigger strategy (high-level vs. staged updates) with iCIMS team, as well as define and validate job closure automation approach • Confirm data model and field mappings (verticals, job brands, reporting structure) • Continue dashboard and reporting build (Workfront-first approach) • Drive stakeholder alignment to support target go-live readiness (July 1 - dependent on identified major blocker)

Blockers

• Trigger limitations from iCIMS impacting full lifecycle automation • Dependency on external stakeholders (iCIMS + Enzo team) for configuration and feasibility • Compliance constraints (PII, restricted access) shaping integration design

P3

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

YELLOW

Harris Poll CSC implementation progressing with UAT largely completed. Functionally on track for go-live, but operational risk remains due to unresolved ownership, process dependencies, and system limitations requiring interim workarounds. Next Steps: • Finalize remaining UAT activities and process standardization. Get UAT sign-off approval • Close outstanding dependencies (e.g., permissions, documentation) to enable full workstream closure • Team agreed to avoid process changes for now, continue validating issues, and escalate unresolved workflow and vendor/integration gaps.

Blockers

Ownership across Finance, business teams, and Central Services is still not fully defined, creating scalability and execution risk. Pending final go-live date.

Leadership Context

Leadership support required to resolve outstanding dependencies and drive stakeholder accountability to complete final UAT/process alignment and enable full transition to steady-state operations. - Technical go-live date alignment - migration approach alignment - Engaging Central Services in workflow design discussion alignment for scalability purpose

Tajana Neve Pidlaoan

Submitted 2026-06-08T10:56:10.416Z

R 0Y 0G 3
3 priority items

Priorities

  • P1 PRJ-036 EUC & RPA Projects
  • P2 PRJ-036 EUC & RPA Projects
  • P3 PRJ-036 EUC & RPA Projects

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-036 EUC & RPA Projects

Unassigned

GREEN

RPA | Kick off call on SOX T&E Audit Automation Initiative - 6/8 QA Session | Workiva - 6/8 Equabot: Kickoff and Demo Allison, Hunter, HarrisX - 6/9 Targeted Victory, Deployed - Hypercare In Progress next week

P2

PRJ-036 EUC & RPA Projects

Unassigned

GREEN

Bizapps Migration Tasks Review & Planning TCR Board creation for EUC Dashboard 1Password Form Creation In Progress Finance Onboarding In Progress IT EUC Onboardings & Offboardings In Progress

P3

PRJ-036 EUC & RPA Projects

Unassigned

GREEN

Maconomy Process Standardization EQUA Pipeline Refining RPA Pipeline Update Internal Weekly Project Update

Archive Reference

Complete archive list for direct week access.

Week EndingGenerated (UTC)Action
2026-06-072026-06-10T17:51:50.713ZViewing
2026-05-242026-05-22T18:34:58.895ZOpen Submission Archive
2026-05-172026-05-22T18:35:51.576ZOpen Submission Archive
2026-05-102026-05-22T18:35:19.325ZOpen Submission Archive
2026-05-032026-05-08T17:20:00.855ZOpen Submission Archive
2026-04-262026-04-27T21:55:44.672ZOpen Submission Archive
2026-04-192026-04-29T17:58:27.785ZOpen Submission Archive
2026-04-122026-04-13T13:22:30.934ZOpen Submission Archive
2026-04-052026-04-06T14:23:12.310ZOpen Submission Archive
2026-03-292026-03-30T13:15:16.542ZOpen Submission Archive
2026-03-222026-03-17T22:25:47.706ZOpen Submission Archive
2026-03-152026-03-16T22:10:16.138ZOpen Submission Archive
2026-03-082026-03-05T22:37:17.288ZOpen Submission Archive
2026-03-012026-03-05T22:37:20.021ZOpen Submission Archive
2026-02-222026-02-25T00:08:55.076ZOpen Submission Archive