SUBMISSIONS

4

(-2)

RED

1

(-2)

Week-over-Week Signals

Compared to 2026-03-15

Deteriorations (0)

No RED or YELLOW deteriorations this week.

New Signals (2)

RED

72andSunny proposed proxy users as resolution for missing users issue c/o Arun. Once added, Arun can migrate tasks completely and Milda can review the dashboards. Red status because the Mar-30 deadline to push dashboards to Prod isn’t po...

YELLOW

Team has working sessions scheduled throughout the week for removing Google and Slack out of Rippling and tying it directly to Okta. This is part of their upcoming UKG Go-Live on 1st week of April.

Resolved (18)
GREEN

- Awaiting updates from Andre to find the availability of the stakeholders to help us schedule a kickoff meeting and discovery session

GREEN

- Migrating users in Group 2; 8 out 10 are done - Next up: Non-manual migrations and a manual migration with the CEO on Friday, March 13 - Next steps: SentinelOne deployment, ZeroTouch deployment, and other apps they need

RED

- Supposed to kick off and proceed to discovery on Friday, 13 March, but Mitch Ross pushed back during the call due to internal discussions that need to happen first and agreed upon before proceeding with the RMM enrolment and MDM migrat...

GREEN

72andSunny's full data migration is completed c/o Arun (pre-req to Milda's final review of 3 dashboards for Prod migration), except for a few tasks due to missing users. Currently being investigated by the agency. 5th dashboard's develop...

GREEN

API integration completed; security review scheduled

13 more items not shown.

Persistent Risks

No persistent risks detected.

Weekly Submission Archive

Read-only source submissions for week ending 2026-03-22.

Casey Younggren

Submitted 2026-03-16T17:18:50.321Z

R 0Y 0G 3Blockers
3 priority items

Priorities

  • P1 PRJ-010 CSC Agency Implementation
  • P2 PRJ-011 AI Enablement
  • P3 PRJ-012 PMO Operations (CSC & CORE IT)

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

GREEN

-Instrument Discovery -Continue scheduling for other new implementations (Welcome Kit for F&B, Welcome Kit and Discovery for Targeted Victory. Line up upcoming UK Discoveries)

Blockers

The only risk so far is regarding lining up the upcoming UK discoveries. Paul is wanting to hit three of them in April (Goodstuff, INK, and Locaria - previously slated for June) however, it really depends on the availability of BOTH agencies, and Odin)

P2

PRJ-011 AI Enablement

Stagwell CSC Program

GREEN

-Schedule 30/60/90 Project Planning session for Veritas and 72. -Work with Claudine on upcoming Copilot Training sessions for CMV.

Blockers

No risks or blockers at the moment - each group is still early in the process.

P3

PRJ-012 PMO Operations (CSC & CORE IT)

Stagwell CSC Program

GREEN

-Work on UKG / Maconomy cleanup slides

Givan Turla

Submitted 2026-03-16T07:17:34.505Z

R 0Y 1G 2Blockers
3 priority items

Priorities

  • P1 PRJ-024 Rhythm - Mediacurrent Merge-Rebrand
  • P2 PRJ-006 Movers & Shakers Onboarding
  • P3 PRJ-023 ADK Merge to Assembly

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-024 Rhythm - Mediacurrent Merge-Rebrand

Communication & Collaboration

GREEN

Entering Phase 2 of the project: Rebrand The domain is 100% warmed up. Team currently have working sessions both internally and with the agency to work on pre-staging applications for the upcoming domain change. Goal is to pre-stage all applications within the next 10 working days.

Blockers

No blockers for now. Risk: Might not reach the April 1st timeline for Workfront as agency wants to be rebranded before going to Workfront. Realistically speaking, it is possible but it would be rushed.

P2

PRJ-006 Movers & Shakers Onboarding

Orchestration & Automation

YELLOW

Team has working sessions scheduled throughout the week for removing Google and Slack out of Rippling and tying it directly to Okta. This is part of their upcoming UKG Go-Live on 1st week of April.

Blockers

No blockers and risks for now. Yellow tag as we are close to go-live date.

P3

PRJ-023 ADK Merge to Assembly

Communication & Collaboration

GREEN

Migration is ongoing for all ADK regions. We already completed migrating 2 years worth of mailbox data. Ongoing migration still for Teams, Sharepoint, and other file repositories. Once migration is finished for the rest of the storage, we will proceed with cutting over/going live per region. Goal is to start the series of cutovers by 1st week of April. (highly dependent on migration speed)

Blockers

Risk: Device procurement. This piece is being handled by Craig, Kevin Whelan, and Forbes. As per last update this is taking longer than expected due to delays in processing the documents on the Assembly side. The risk is the devices are made to order and it would take time to ship these devices to the regions before June. We are running the risk of these users not being able to work by June.

Kirsten Margarette Lagura

Submitted 2026-03-20T22:20:04.886Z

R 1Y 0G 2Blockers
3 priority items

Priorities

  • P1 PRJ-010 CSC Agency Implementation
  • P2 PRJ-010 CSC Agency Implementation
  • P3 PRJ-019 CSC Systems Integration

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

RED

72andSunny proposed proxy users as resolution for missing users issue c/o Arun. Once added, Arun can migrate tasks completely and Milda can review the dashboards. Red status because the Mar-30 deadline to push dashboards to Prod isn’t possible now.

Blockers

Jessica still hasn’t provided the table/field data mappings needed to resolve the Periodic Budget/Cost Rates issue for the Dashboards.

Leadership Context

Original Mar-31 target date for 3 dashboard’ Production migration needs to be revisited.

P2

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

GREEN

Code & Theory’s agency support queue is consistently being monitored, and issues assigned to the Stagwell team are addressed or resolved accordingly. It was confirmed through Jessica that Maconomy Support is also providing support to the agency.

Blockers

There was a delay from the agency side the past few days due to the holiday in India on Thursday and holiday in the Philippines on Friday.

Leadership Context

Tickets causing Code to not be able to function as they did in Grail are 1) user issues pending in Maconomy (action item c/o both Code & Maconomy), and 2) migration/set-up issues to be addressed by the agency.

P3

PRJ-019 CSC Systems Integration

Stagwell CSC Program

GREEN

Subham completed the technical sections of the Scope Doc v2, and I sent out the WBS draft for Adobe & Stagwell’s review. Meeting on Monday with Subham and Manoj to finalize the project plan on Workfront. Within next week, the scope doc and project plan will be out for review by the rest of the team.

Blockers

Manoj is the sole resource responsible for the Data Warehouse spanning 1/2 of the WBS with multiple projects he’s working on in parallel. It’s understood that this likely won’t be prioritized if the other projects urgently need his attention.

Leadership Context

Once the project plan is in place, we’ll have a target date to work towards. Target is to have this finalized within next week.

Krizzia Vic Amparo

Submitted 2026-03-20T22:43:14.615Z

R 0Y 0G 3Blockers
3 priority items

Priorities

  • P1 PRJ-010 CSC Agency Implementation
  • P2 PRJ-015 Stagwell LMS - ALM
  • P3 PRJ-010 CSC Agency Implementation

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

GREEN

Doner Agency: CAB Timesheet Sync (Maconomy → Workfront): Job status mismatch under review; Adobe scoping in progress. Fusion‑Driven Intake & Routing: AI‑driven intake concept validated; architecture deep dive rescheduled with Doner/Doug. Custom Sheet Task Reporting: App Builder approach confirmed; Adobe to own build and specs. Project Boards: Pain points identified; initial demo done. Second priority for Doner post‑Timesheet UAT. Asset Migration (Xinet/Box → AEM): Asset list, folder structure, and metadata sample provided ahead of initial TP scheduled next week BI Dashboard Inventory:Reuse of 72andSunny dashboards under review. Dashboard inventory in-progress. Next Steps: • Adobe to finalize scoping for Timesheet Sync approach • Complete Fusion architecture deep dive • Define Asset Migration scope and timeline; create WF plan • BI to release dashboard inventory for agency review

Blockers

n/a

P2

PRJ-015 Stagwell LMS - ALM

Communication & Collaboration

GREEN

• CSC Learning Path: CSC learning path structure being transposed into ALM. (Build) • ALM Ways of Working: Transition planning completed. • Harris X: Learning path curation and access setup in progress; modules published and LMS branding configured. • Movers + Shakers: ALM walkthrough completed to support agency readiness. • OneStream: Train‑the‑Trainer session completed. Working on building the learning path and modules. • Crispin: CSC materials access granted; branding updates in progress. • Assembly: Initial walkthrough completed; onboarding and MediaOcean training setup initiated; core LMS access provisioned. Next Steps: • Finalize CSC learning path governance and publish in ALM • Schedule Harris X focused LMS demo • Grant M+S Admin/Author access post‑UKG go‑live • Define Crispin learning path and branding • Align on MediaOcean integration approach for Assembly

Blockers

N/a

P3

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

GREEN

CMV — Timesheets / Integration:CAB enhancements in progress to resolve Maconomy ↔ Workfront timesheet inconsistencies and align WF settings with Doner standards; solution intended to scale across agencies.(In-progress) UNR — Solution Alignment:Solution design under internal review; Sandbox access issue identified and addressed (Google SSO required). Awaiting UNR access confirmation. (In Progress) CREATE:Status cadence being established; awaiting agency confirmation on meeting details. (Pending) Next Steps: -Finalize Adobe scoping for CMV timesheet enhancements -Confirm UNR Sandbox access via Google SSO -Lock CREATE status call schedule

Blockers

Risk: CSC timeline and scope change for UNR agency

Archive Reference

Complete archive list for direct week access.

Week EndingGenerated (UTC)Action
2026-04-122026-04-13T13:22:30.934ZOpen Submission Archive
2026-04-052026-04-06T14:23:12.310ZOpen Submission Archive
2026-03-292026-03-30T13:15:16.542ZOpen Submission Archive
2026-03-222026-03-17T22:25:47.706ZViewing
2026-03-152026-03-16T22:10:16.138ZOpen Submission Archive
2026-03-082026-03-05T22:37:17.288ZOpen Submission Archive
2026-03-012026-03-05T22:37:20.021ZOpen Submission Archive
2026-02-222026-02-25T00:08:55.076ZOpen Submission Archive