SUBMISSIONS
7
(+3)
Week Ending 2026-04-19
Digest generated at 2026-04-29T17:58:27.785Z
SUBMISSIONS
7
(+3)
RED
1
(-2)
Compared to 2026-04-12
No RED or YELLOW deteriorations this week.
72andSunny's dashboard progress is still on hold. We're still waiting for the PBI team to provide the updated formulas for sign-off. The data migration on the other hand is progressing well and quickly. Kantata data has been fully migrat...
Anomaly: working on finalizing sol design. Anomaly has also completed their Maconomy User Cleanup. TEAM: Had their first Stagwell status call today. They are mostly complete with their Maconomy user cleanup. Current focus: planning comms...
EAC Automation project timeline needs updating. After meeting with Dhruv, Subham identified changes to the Fusion scenarios initially planned with Anthony. The Data Warehouse is no longer a risk; the PBI team confirmed they can proceed w...
Harris Poll: Current Status • UAT kick‑off and technical go‑live timelines shifted due to onboarding delays and recent organizational changes • Governance stabilized with a recurring cadence call to track progress, align next steps, and...
Mitigation plan - Ed will proceed and default their user type to employee (lowest level) instead, and then go-live within - Once they give the piece of information that we need, that's the only time we'll use it for onboarding/offboardin...
- Kicked off with Consulum - Project is on hold
- Kicked off with JetFuel - Did the initial Discovery session with the stakeholders - A master migration document with device lists was shared in chat - The agency teams were requested to complete their assigned device information.
- Non‑manual Jamf migrations are complete - Cleanup of legacy apps is finished
Antonio and I are continuously aligning on building out the deck for the 72andSunny presentation. We are targeting to do the kickoff next week.
CMV: - Monday → Workfront Migration: Scope review completed and confirmed that a full migration is no longer required. Yamamoto has list of Programs and Projects provided to Daniel for migration via kickstart. Yamamoto is currently compl...
7 more items not shown.
No persistent risks detected.
Read-only source submissions for week ending 2026-04-19.
Submitted 2026-04-17T17:09:29.106Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Networking Dev Ops
Blockers
Leadership Context
P2
Orchestration & Automation
Blockers
Leadership Context
P3
Networking Dev Ops
Blockers
Leadership Context
Submitted 2026-04-17T20:31:43.714Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
Leadership Support
Reason
RISK_ESCALATION
Timing
URGENT
Notes
I have not heard back on my last reply to Goodstuff. I do not know how to lock this in prior to our discussion with them scheduled for Thursday next week. For NRG - I would like assistance or ideas on how to move forward, that is not my realm. I can help support that, but the decision does not come from me. I am blocked on their pushback until they agree to participate in CSC.
P1
Stagwell CSC Program
Blockers
P2
Stagwell CSC Program
P3
Stagwell CSC Program
Submitted 2026-04-14T18:28:01.554Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Orchestration & Automation
Blockers
P2
Orchestration & Automation
Blockers
Leadership Context
P3
Orchestration & Automation
Blockers
Submitted 2026-04-13T14:17:41.651Z
Updated 2026-04-17T18:15:40.759Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Communication & Collaboration
Blockers
P2
SaaS
Blockers
P3
Communication & Collaboration
Submitted 2026-04-17T18:46:04.847Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
Leadership Support
Reason
DEPENDENCY_UNBLOCK
Timing
URGENT
Notes
72&Sunny 2 dashboard blockers: 1) PBI team hasn’t provided the updated formulas document needed for agency sign-off, blocking Prod deployment of 3 completed dashboards; 2) Maconomy team hasn’t provided the required data/field mapping, blocking completion of the remaining dashboards.
P1
Stagwell CSC Program
Blockers
Leadership Context
P2
Stagwell CSC Program
P3
Stagwell CSC Program
Blockers
Submitted 2026-04-17T21:04:11.814Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Stagwell CSC Program
Blockers
Leadership Context
P2
Stagwell CSC Program
Blockers
Leadership Context
P3
Stagwell CSC Program
Blockers
Leadership Context
Submitted 2026-04-17T18:13:10.241Z
Priorities
Expand to view descriptions, blockers, and leadership support.
Collapse archive details.
P1
Unassigned
P2
Unassigned
P3
Unassigned
Complete archive list for direct week access.
| Week Ending | Generated (UTC) | Action |
|---|---|---|
| 2026-06-07 | 2026-06-10T17:51:50.713Z | Open Submission Archive |
| 2026-05-24 | 2026-05-22T18:34:58.895Z | Open Submission Archive |
| 2026-05-17 | 2026-05-22T18:35:51.576Z | Open Submission Archive |
| 2026-05-10 | 2026-05-22T18:35:19.325Z | Open Submission Archive |
| 2026-05-03 | 2026-05-08T17:20:00.855Z | Open Submission Archive |
| 2026-04-26 | 2026-04-27T21:55:44.672Z | Open Submission Archive |
| 2026-04-19 | 2026-04-29T17:58:27.785Z | Viewing |
| 2026-04-12 | 2026-04-13T13:22:30.934Z | Open Submission Archive |
| 2026-04-05 | 2026-04-06T14:23:12.310Z | Open Submission Archive |
| 2026-03-29 | 2026-03-30T13:15:16.542Z | Open Submission Archive |
| 2026-03-22 | 2026-03-17T22:25:47.706Z | Open Submission Archive |
| 2026-03-15 | 2026-03-16T22:10:16.138Z | Open Submission Archive |
| 2026-03-08 | 2026-03-05T22:37:17.288Z | Open Submission Archive |
| 2026-03-01 | 2026-03-05T22:37:20.021Z | Open Submission Archive |
| 2026-02-22 | 2026-02-25T00:08:55.076Z | Open Submission Archive |