Week Ending 2026-05-10

Digest generated at 2026-05-22T18:35:19.325Z

SUBMISSIONS

6

(+1)

RED

0

(-1)

Week-over-Week Signals

Compared to 2026-05-03

Deteriorations (0)

No RED or YELLOW deteriorations this week.

New Signals (4)

YELLOW

14 Macs and ~4 PCs were enrolled this week, with remaining users requiring direct follow-up. A managed Apple ID approach was identified to address concerns around personal Apple ID data during enrollment. The team confirmed the JetFuelSt...

YELLOW

Progress Harris Poll: Build → UAT: Final pre‑UAT items closed; on track to start UAT next week (week of May 11). UAT Prep: End‑to‑end demo recording in progress for tester walkthroughs. Workfront–Maconomy: Migration approach confirmed; n...

YELLOW

Team - things are good on their end Anomaly - things are good for them, they had a change mgmt meeting yesterday - I got them UKG info Odin was asking for. They are on track Instrument - still need solution design approval This week - go...

YELLOW

Wall racks have been moved onsite. Comcast is scheduled for May 14 to wire the MPOE and run fiber to the 4th floor. Security cabling and Crowe cabling are actively in progress. Missing equipment was recovered, providing enough PDUs, UPSs...

Resolved (15)
GREEN

All the necessary applications were discussed and pre-staged this week. Next week we will focus on comms dissemination, and identifying a go-live to move the apps over from Maru Okta tenant to Harris Poll

GREEN

Cameras, firewall, and access points are installed and operational. Network and conferencing systems are up and running. Temporary reuse of older equipment has enabled site readiness while new devices are arriving onsite. ISP relocation...

GREEN

Doner Asset Migration (Xinet/Box → AEM): The Stagwell team has successfully set up and connected to the GCP VM. Doner is still finalizing assets and metadata and will notify Stagwell once they are ready to proceed with the pilot migratio...

GREEN

EUC | Stagwell Onboarding & Induction Items process & procedure unification, In Progress - We are trying to unify the onboarding process for all employee type across Stagwell. EUC | BizApps Migration Project, Planning - We are awaiting o...

GREEN

Final meeting before cutover happened this week with the agency. We were able to set expectations for the go-live happening on night of May 5th. I have also prepared and lined up all necessary changes that needs to happen for the night o...

10 more items not shown.

Persistent Risks

No persistent risks detected.

Weekly Submission Archive

Read-only source submissions for week ending 2026-05-10.

Arriana Pabalate

Submitted 2026-05-08T22:21:10.364Z

R 0Y 2G 1Blockers
3 priority items

Priorities

  • P1 PRJ-008 Team - Jetfuel Onboarding
  • P2 PRJ-034 Stagwell Global - Minneapolis Hub
  • P3 PRJ-025 Stagwell Global - Singapore Office Hub

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-008 Team - Jetfuel Onboarding

Orchestration & Automation

YELLOW

14 Macs and ~4 PCs were enrolled this week, with remaining users requiring direct follow-up. A managed Apple ID approach was identified to address concerns around personal Apple ID data during enrollment. The team confirmed the JetFuelStudio.com domain takeover and Okta federation will run in parallel with the Google → M365 migration and will not impact cutover timing. SentinelOne rollout planning is underway, beginning with a pilot after enrollment completion. June 16 remains the tentative go-live date driving communications and training planning.

Blockers

Some users remain hesitant to enroll devices due to personal Apple ID concerns. Remaining device enrollment requires targeted outreach and coordination. Device procurement for upcoming hires may take over a week, and mailbox conversion during migration could create tooling disruption and increase rework/costs.

Leadership Context

June 16 continues to serve as the anchor milestone for migration readiness, communications, and training. Broader identity and application consolidation efforts include Okta federation, Box migration under Okta, and cleanup of old or unused applications.

P2

PRJ-034 Stagwell Global - Minneapolis Hub

Networking Dev Ops

YELLOW

Wall racks have been moved onsite. Comcast is scheduled for May 14 to wire the MPOE and run fiber to the 4th floor. Security cabling and Crowe cabling are actively in progress. Missing equipment was recovered, providing enough PDUs, UPSs, and racks for deployment. Orchestration go-live remains on track, and the team is actively working to migrate AD in order to avoid standing up new on-prem infrastructure in the new environment.

Blockers

Meraki network deployment is still pending delivery and finance/payment processing. Rack installation scheduling still requires confirmation and coordination ahead of the Comcast visit. Broader office move timing may shift toward mid-August due to furniture delays, though no material impact to Orch requirements has been identified at this time.

Leadership Context

Timeline risk is currently considered low, with focus remaining on ensuring 4th-floor rack readiness ahead of Comcast installation activities. Leadership has also approved additional server room workbench purchases once space allocation is finalized.

P3

PRJ-025 Stagwell Global - Singapore Office Hub

Networking Dev Ops

GREEN

The site is operational and near completion. Firewall installation has been completed, with only final configuration work by Harry (Palo Alto) remaining before project closeout. The team is also awaiting delivery of approximately 100 access cards from JLL.

Blockers

Final firewall configuration remains dependent on Palo Alto resolving a cloud-side issue. Loaner equipment remains in use until configuration is completed and production equipment can be finalized.

Leadership Context

The project is in its final stabilization phase with minimal remaining effort. Access card delivery is being tracked operationally but is not considered a formal project dependency. Once firewall configuration is completed, the Singapore hub can be considered fully complete.

Casey Younggren

Submitted 2026-05-08T13:05:07.355Z

R 0Y 1G 2Blockers
3 priority items

Priorities

  • P1 PRJ-010 CSC Agency Implementation
  • P2 PRJ-011 AI Enablement
  • P3 PRJ-014 Global Projects Team Coordination

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

YELLOW

Team - things are good on their end Anomaly - things are good for them, they had a change mgmt meeting yesterday - I got them UKG info Odin was asking for. They are on track Instrument - still need solution design approval This week - got left field labs brief confirmed (5/18) and Veritas (5/26) Redscout had their exec briefing on Monday 5/6 Targeted Victory had their welc. kit Monday 5/6 - discovery next week Locaria has confirmed that 6/15 week works for them - IP on getting welcome kit on calendar. GALE is working on their core team before next steps.

Blockers

Goodstuff has now determined they need to pause. NRG has been pushed to Jan 2027

P2

PRJ-011 AI Enablement

Stagwell CSC Program

GREEN

Working in coordination with the reply team. Still trying to get CMV their sessions, Hunter is doing theirs and it is going well. Working now to get Adobe sessions out for Hunter (Hunter has requested these) and reply sessions for Stg. Corporate.

P3

PRJ-014 Global Projects Team Coordination

Stagwell CSC Program

GREEN

Pain points list coordination. Met with BP's to see how I can support them with Garrett and Erm out. Met with Sara Bank (Adobe) to give her a rundown of the workings of CSC - agency process etc.

Giuseppe Enriquez

Submitted 2026-05-08T23:06:14.871Z

R 0Y 0G 3Blockers
3 priority items

Priorities

  • P1 PRJ-008 Team - Jetfuel Onboarding
  • P2 PRJ-021 Consulum Onboarding
  • P3 PRJ-034 Stagwell Global - Minneapolis Hub

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-008 Team - Jetfuel Onboarding

Orchestration & Automation

GREEN

Combining Infra and Orch Weekly Sync with JetFuel moving forward to ease up alignment Enrollment Status - Andre sent an email this morning - 13 machines enrolled (Mac); 4 machines enrolled (PC) out of 35 employees Apple Managed Accounts & Domain Migration Complete device enrollment first, then: - Capture JetFuel domain in Apple - Federate to Okta - Launch a 30-day automated migration process - Personal Apple accounts using work emails must: 1. Transfer or retain personal data separately 2. Move to managed accounts Post-Enrollment - Deploy SentinelOne across devices - Silent rollout after testing on pilot users - Minimal user disruption expected New Hire & Device Onboarding Process - Devices enrolled via Apple Business Manager (ABM) + Jamf - Automatic enrollment, app installation, configuration on first boot Cutover Date - Tue June 16

Blockers

No Blockers Risk - Enrollment is progressing but still requires follow-ups. - Users are hesitant due to personal iCloud accounts tied to work emails. Mitigation - Create managed Apple accounts so users can switch from personal accounts and enroll. - Enrollment status will be tracked in the master migration document with a new column.

P2

PRJ-021 Consulum Onboarding

Orchestration & Automation

GREEN

- Discovery session with Consulum - Paul now gained access to ABM and Jamf instance - Got all the important information from Consulum - We'll just follow up with other questions based on the Master Migration Doc while exploring on ABM and Jamf

Blockers

None right now

P3

PRJ-034 Stagwell Global - Minneapolis Hub

Networking Dev Ops

GREEN

The migration piece is technically ready on both PC and Mac sides, but: - Execution is paused due to RADIUS dependency - Mac environment is fully prepared and ready for rollout - PC testing is nearly complete, pending a valid user-based test - The team is following a controlled rollout strategy (pilot → full deployment) Immediate focus is: - Resolving RADIUS issues - Validating infrastructure readiness before cutover Action Items - Assign real user to test PC and run migration - Manny & Gael - Validate RADIUS readiness (Okta integration) - Harry and Jeremy - Confirm RADIUS profile deployment via Ninja - Manny - Conduct RADIUS troubleshooting session - Infra - Begin Mac pilot migration (once dependency cleared) - Orch - Identify test users for pilot migrations - UAT

Blockers

None

Givan Turla

Submitted 2026-05-08T23:03:46.160Z

R 0Y 0G 3
3 priority items

Priorities

  • P1 PRJ-021 Consulum Onboarding
  • P2 PRJ-024 Rhythm - Mediacurrent Merge-Rebrand
  • P3 PRJ-028 Sportbeach Onboarding

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-021 Consulum Onboarding

Orchestration & Automation

GREEN

We were able to successfully integrate M365 and Adobe to Consulum this week. We have a meeting to discuss Proofpoint next week to proceed with the deployment. Goal is to onboard them on Proofpoint within May After that we will hand over them to Orchestration team for Device Management onboarding.

P2

PRJ-024 Rhythm - Mediacurrent Merge-Rebrand

Communication & Collaboration

GREEN

We successfully rebranded Mediacurrent to Current Agency this week. We will be monitoring the support channel until the following week because of Workfront. This is the first time we went live with a project with full effect of change in Workfront, hence the extended support for Mediacurrent.

P3

PRJ-028 Sportbeach Onboarding

SaaS

GREEN

WE were able to meet with the Sportbeach team this week to align on next steps for the project. We would pause the deployment until they align with legal about the validity of data migration for certain accounts. Next week, we will continue to cooperate with Antonio to facilitate discussions on strategy regarding to their full switch to SB accounts. Goal is to switch them fully to SB accounts, before or after Cannes Film Festival (July 2026)

Krizzia Vic Amparo

Submitted 2026-05-08T21:42:37.738Z

R 0Y 1G 2Blockers
3 priority items

Priorities

  • P1 PRJ-010 CSC Agency Implementation
  • P2 PRJ-010 CSC Agency Implementation
  • P3 PRJ-010 CSC Agency Implementation

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

GREEN

Doner Asset Migration (Xinet/Box → AEM): Stagwell and Adobe had a call to align the changes on the metadata schema. Changes have been deployed on the production. Stagwell plans to start migrating the folder that Doner is about give the heads up for. This will also help identify if any script modifications are needed, so we can make those adjustments accordingly. Additionally, we're exploring ways to handle the PSB files. Next steps: We have a scheduled Adobe/Stagwell + Jenn call this coming Tuesday, 5/12 to align between Adobe/Stagwell + Doner on how we approach the metadata migration in preparation for asset migration. Afterwhich, Jenn to provide go signal with pilot assets. Fusion AI–Driven Intake: UAT walkthrough session with Doner completed. Ongoing UAT with Doner - ETA 5/11. Next steps: Once UAT has been completed, Doner to provide sign-off approval to move the scenario to production environment(live). Project Boards: This remains a Priority 2 item. Teams will reconvene to review requirements and walk through sample project boards, including any examples Adobe may provide. This is tentatively targeted for May, following completion of the Timesheet multi-threading UAT.

Blockers

Project Board Blocker - Maconomy Timesheet activation UAT completion

Leadership Context

n/a

P2

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

GREEN

Stagwell HR/Recruitment: • Pre-hire automation approach finalized ○ Extends lifecycle tracking (TA review → offer) using existing Workfront templates/forms • Integration design confirmed (iCIMS → Workfront) ○ Trigger at job creation/assignment with recurring sync (~3–4 hrs) ○ Technical approach validated (Search API + Fusion, status log capture) • Reporting & capacity model direction set ○ Focus on recruiter workload, capacity, and agency allocation visibility • Sandbox-first delivery aligned ○ Build → pilot (5–10 jobs) → validate → production • Stakeholder alignment in progress ○ Weekly cadence active; requirements captured for reporting, users, and structure • Technical readiness progressing ○ iCIMS API access secured; CAB initiated Next Steps Finalize process documentation + reporting requirements Complete API analysis + data mapping Configure custom forms/templates in sandbox Build + pilot pre-hire automation (5–10 job profiles) Align timeline, onboarding, and stakeholder sign-off

Blockers

• Pending HR inputs (Nick): reporting requirements, agency/vertical list, user list • Resource management model (hours vs. points) requires validation API/data access constraints impacting final mapping and build readiness

P3

PRJ-010 CSC Agency Implementation

Stagwell CSC Program

YELLOW

Progress Harris Poll: Build → UAT: Final pre‑UAT items closed; on track to start UAT next week (week of May 11). UAT Prep: End‑to‑end demo recording in progress for tester walkthroughs. Workfront–Maconomy: Migration approach confirmed; no technical blockers for UAT. AI Enablement: BERA.ai enablement completed; no longer a dependency. -Deliver and distribute UAT demo recording (by EOW). - Finalize UAT participant list and session schedule. - Secure ContractSafe approval (or initiate procurement); escalate if needed. CSC + Harris Poll: Hold change‑management planning session ahead of go‑live.

Blockers

ContractSafe: License approval pending (~$10K–$22K). Procurement escalation may be required; delay could impact timeline. Tango: CSC will not absorb cost; Harris Poll decision outstanding.

Tajana Neve Pidlaoan

Submitted 2026-05-08T15:35:12.117Z

R 0Y 0G 3Blockers
3 priority items

Priorities

  • P1 PRJ-012 PMO Operations (CSC & CORE IT)
  • P2 PRJ-012 PMO Operations (CSC & CORE IT)
  • P3 PRJ-012 PMO Operations (CSC & CORE IT)

Expand to view descriptions, blockers, and leadership support.

P1

PRJ-012 PMO Operations (CSC & CORE IT)

Stagwell CSC Program

GREEN

RPA Updates Bizapps Migration Project Discussion on Monday Maconomy Upgrade Preparation - Regression Testing to be done next week IC Allocation Phase 2 - Done on the estimation, ready for development EQUA Projects - To create Project Pipeline via JIRA, Assign workflows and set up VIVA Projects - To align with the project pipeline doc from Rebecca Maconomy Process Alignment & Standardization next week with Rebecca and Colleen Prisma - Allegory, TargetCast, TradeX - Discovery Phase Maconomy - PMX, TSA, Grason - Ongoing on Hypercare Maconomy - Crispin - Ongoing on Development

Blockers

RPA Demo - Cloud PC License access. The more this is delayed, the delivery date will be push back even further. The stakeholder is no longer happy since this is very delayed already. We can't afford any more delays.

P2

PRJ-012 PMO Operations (CSC & CORE IT)

Stagwell CSC Program

GREEN

RPA EQUA Project Pipeline - To set this up next week and list all ongoing and deployed projects Bizapps Migration - Build out the next steps on JIRA, Schedule call for alignment

P3

PRJ-012 PMO Operations (CSC & CORE IT)

Stagwell CSC Program

GREEN

Will start connecting with Rebecca to gather project requirements and pass over to the team. I'll start transitioning in getting all necessary information to start projects. I'll be refining JIRA spaces, workflows, and etc. depending on the projects.

Archive Reference

Complete archive list for direct week access.

Week EndingGenerated (UTC)Action
2026-06-072026-06-10T17:51:50.713ZOpen Submission Archive
2026-05-242026-05-22T18:34:58.895ZOpen Submission Archive
2026-05-172026-05-22T18:35:51.576ZOpen Submission Archive
2026-05-102026-05-22T18:35:19.325ZViewing
2026-05-032026-05-08T17:20:00.855ZOpen Submission Archive
2026-04-262026-04-27T21:55:44.672ZOpen Submission Archive
2026-04-192026-04-29T17:58:27.785ZOpen Submission Archive
2026-04-122026-04-13T13:22:30.934ZOpen Submission Archive
2026-04-052026-04-06T14:23:12.310ZOpen Submission Archive
2026-03-292026-03-30T13:15:16.542ZOpen Submission Archive
2026-03-222026-03-17T22:25:47.706ZOpen Submission Archive
2026-03-152026-03-16T22:10:16.138ZOpen Submission Archive
2026-03-082026-03-05T22:37:17.288ZOpen Submission Archive
2026-03-012026-03-05T22:37:20.021ZOpen Submission Archive
2026-02-222026-02-25T00:08:55.076ZOpen Submission Archive