Ops Pulse

AI-generated interpretation for week ending 2026-05-17. Canonical digest data remains the source of truth.

Risk Concentration

Portfolio exposure analysis centered on shared blockers, recurring risks, and leadership intervention signals.

Operator Focus

Operator attention distribution analysis across dependency coordination, delivery friction, planning shifts, and issue resolution.

Executive Brief 2026-05-17

Generated: 2026-05-22T18:35:51.576Z

Executive Brief

PORTFOLIO NARRATIVE

Risk is rising as deteriorations outpace improvements.

DET_DETERIORATIONS · HIGH

Week Ending

2026-05-17

Health Score

83 (-8)

RAG Totals

RED 3 · YELLOW 3 · GREEN 15

Leadership Actions

0 (Decision Required 0)

New Risks

0

Deteriorations

1

Coverage

7/11

Portfolio Trends

Last 12 weeks of portfolio direction.

Portfolio Health Trend

050100Week Ending 2026-03-01: 10003-01Week Ending 2026-03-08: 80Week Ending 2026-03-15: 7603-15Week Ending 2026-03-22: 90Week Ending 2026-03-29: 9003-29Week Ending 2026-04-05: 87Week Ending 2026-04-12: 7304-12Week Ending 2026-04-19: 89Week Ending 2026-04-26: 8204-26Week Ending 2026-05-03: 87Week Ending 2026-05-10: 9105-10Week Ending 2026-05-17: 8305-17

RED Priority Trend

023Week Ending 2026-03-01: 003-01Week Ending 2026-03-08: 1Week Ending 2026-03-15: 303-15Week Ending 2026-03-22: 1Week Ending 2026-03-29: 103-29Week Ending 2026-04-05: 0Week Ending 2026-04-12: 304-12Week Ending 2026-04-19: 1Week Ending 2026-04-26: 104-26Week Ending 2026-05-03: 1Week Ending 2026-05-10: 005-10Week Ending 2026-05-17: 305-17

Priority Volume Trend

01121Week Ending 2026-03-01: 303-01Week Ending 2026-03-08: 6Week Ending 2026-03-15: 1803-15Week Ending 2026-03-22: 12Week Ending 2026-03-29: 2103-29Week Ending 2026-04-05: 15Week Ending 2026-04-12: 1204-12Week Ending 2026-04-19: 21Week Ending 2026-04-26: 1804-26Week Ending 2026-05-03: 15Week Ending 2026-05-10: 1805-10Week Ending 2026-05-17: 2105-17
View Full Briefing ↓

PORTFOLIO NARRATIVE

Risk is rising as deteriorations outpace improvements.

DET_DETERIORATIONS · HIGH

PORTFOLIO SIGNAL

Health Score

83

Change vs Last Week

-8

RED

3

YELLOW

3

GREEN

15

Submissions Coverage

7 / 11

Total Priorities Captured

21

WHAT CHANGED

RED

+3

YELLOW

-1

GREEN

+1

New Risks

0

Improvements

1

Deteriorations

1

EXECUTIVE ACTIONS

No leadership actions required.

PROJECT MOVEMENTS

Arriana Pabalate

PRJ-034 Stagwell Global - Minneapolis Hub [YELLOW]

Progress

Installation activity is ongoing with ISP setup work in progress and coordination happening on-site. Physical constraints from unexpected ducting placement are affecting the planned rack location. Network equipment has largely arrived on si...

Expand

Installation activity is ongoing with ISP setup work in progress and coordination happening on-site. Physical constraints from unexpected ducting placement are affecting the planned rack location. Network equipment has largely arrived on site. Switch compatibility is still under review with an alternative option being evaluated pending a quote. Additional vendor installations are scheduled but dependent on-site readiness. Rack installation is planned but not yet completed.

Blocker

Physical ducting placement is impacting rack positioning. Switch compatibility decision is still pending. Vendor timelines remain dependent on site readiness.

Context

Site readiness and network design decisions are the primary dependencies impacting installation sequencing and deployment progress.

Casey Younggren

PRJ-010 CSC Agency Implementation [GREEN]

Progress

Biggest focus this week is the Targeted Victory Discovery.

Dayne Smith

PRJ-010 CSC Agency Implementation [RED]

Progress

72 and Sunny Dashboards Two Week Sprint - Monday Client Working Session - Requirements Gathering - Made progress on 4 dashboards Tuesday Client Working Session - Proceed with remaining dashboards & Project Scope Technical Doc send to Agency...

Expand

72 and Sunny Dashboards Two Week Sprint - Monday Client Working Session - Requirements Gathering - Made progress on 4 dashboards Tuesday Client Working Session - Proceed with remaining dashboards & Project Scope Technical Doc send to Agency for approval. Wedenesday Working Session 1

Blocker

RISK: Technical Doc Sign Off & Maconomy Mapping File

Context

All other priorities are not a focus

Giuseppe Enriquez

PRJ-008 Team - Jetfuel Onboarding [GREEN]

Progress

Endpoint and Device Migration - 5 users remain unenrolled - Requested Andre to keep pushing for the remaining employees to enroll by Friday as a hard deadline - Requested Ralph to give an extra push to follow up on those individuals by afte...

Expand

Endpoint and Device Migration - 5 users remain unenrolled - Requested Andre to keep pushing for the remaining employees to enroll by Friday as a hard deadline - Requested Ralph to give an extra push to follow up on those individuals by afternoon - Give Ralph a list of the remaining users by Friday to send a targeted follow-up message/email to drive completion Apart from the 5 users: - Kristen mentioned Bailey Huff and Gab Auerbach's devices were not on the list - Andre is currently reconfiguring Bailey's machine; will add to the list after setup - Grace and Amanda (Jetfuel) will find and take care of enrolling Gab Auerbach's machine when they find it

Blocker

None right now.

John Louie

PRJ-031 Project Management Onboarding [GREEN]

Progress

Completed Week 4 training activities. Conducted a 1-on-1 meeting with Shannon to discuss and align on the proposed Q2 and Q3 project priorities and initiatives. Also had multiple impromptu working sessions with David to gain further underst...

Expand

Completed Week 4 training activities. Conducted a 1-on-1 meeting with Shannon to discuss and align on the proposed Q2 and Q3 project priorities and initiatives. Also had multiple impromptu working sessions with David to gain further understanding of his ongoing initiatives, reporting processes, and active tickets. Alignment was set that all items and concerns are acknowledged; however, efforts will be prioritized and structured accordingly as the upcoming weeks will focus on projects targeted for Q2 and Q3 delivery.

Blocker

Not really a risk but seeing all things that David present impromtu, I need to manage his expectations and make sure that he understands that we will start to put a structure in place to make sure that would be able to achieve and track goa...

Expand

Not really a risk but seeing all things that David present impromtu, I need to manage his expectations and make sure that he understands that we will start to put a structure in place to make sure that would be able to achieve and track goals as we progress throughout the end of year.

Context

No major risks identified at the moment. However, based on the numerous impromptu items and initiatives raised by David, expectation setting and prioritization alignment are needed to ensure proper structure, tracking, and achievable goals...

Expand

No major risks identified at the moment. However, based on the numerous impromptu items and initiatives raised by David, expectation setting and prioritization alignment are needed to ensure proper structure, tracking, and achievable goals are maintained throughout the remainder of the year.

Kirsten Margarette Lagura

PRJ-010 CSC Agency Implementation [GREEN]

Progress

8 dashboards on track for 05/21. Tony set to complete the new dataset by Tuesday. Arun to validate the sample shared today by Monday, with Manoj preparing tables so Ravi can start creating the dashboards. UAT plan to be created by Monday. T...

Expand

8 dashboards on track for 05/21. Tony set to complete the new dataset by Tuesday. Arun to validate the sample shared today by Monday, with Manoj preparing tables so Ravi can start creating the dashboards. UAT plan to be created by Monday. Tasks & questions will continue to be documented through Workfront. Target is for UAT to start on May 20.

Blocker

BI team only having 3 days (May 18-20) to complete 8 dashboards is high risk.

Context

Commitment to stakeholders is have the 8 dashboards ready for Production deployment by May 21.

Tajana Neve Pidlaoan

PRJ-036 EUC & RPA Projects [YELLOW]

Progress

ACIIFOTECH Offboarding Workiva Kick Off Call, Project start next Monday (Highly important in our team) Maconomy testing for failed automation, resolution before the scheduled Maconomy upgrade IC Allocation Phase 2 is ongoing for development

Context

The Workiva project will be handed over to a new automation team, we need to re-align again so we can deliver in full confidence and on time. This project has been delayed multiple times already by the previous team.