Digest Control
Week Ending 2026-03-29
Submissions
7/10
Priorities
21
Digest
Up to Date
Latest Submission
2026-03-27T14:15:06.928Z
Digest: Up to Date
Digest reflects the current submission set.
Ops Pulse
AI-generated interpretation for week ending 2026-03-29. Canonical digest data remains the source of truth.
Risk Concentration
Portfolio exposure analysis centered on shared blockers, recurring risks, and leadership intervention signals.
Operator Focus
Operator attention distribution analysis across dependency coordination, delivery friction, planning shifts, and issue resolution.
Executive Brief — 2026-03-29
Generated: 2026-03-30T13:15:16.542Z
Executive Brief
PORTFOLIO NARRATIVE
Portfolio is stable, but decision pressure remains active.
STB_DECISIONS · HIGH
Week Ending
2026-03-29
Health Score
90 (0)
RAG Totals
RED 1 · YELLOW 3 · GREEN 17
Leadership Actions
2 (Decision Required 1)
New Risks
0
Deteriorations
0
Coverage
7/10
Portfolio Trends
Last 12 weeks of portfolio direction.
RED Priority Trend
Priority Volume Trend
View Full Briefing ↓Collapse Briefing ↑
PORTFOLIO NARRATIVE
Portfolio is stable, but decision pressure remains active.
STB_DECISIONS · HIGH
PORTFOLIO SIGNAL
Health Score
90
Change vs Last Week
0
RED
1
YELLOW
3
GREEN
17
Submissions Coverage
7 / 10
Total Priorities Captured
21
WHAT CHANGED
RED
0
YELLOW
+2
GREEN
+7
New Risks
0
Improvements
0
Deteriorations
0
EXECUTIVE ACTIONS
Decision Required
Dayne Smith — PRJ-004 Echo
Notes: awefa
Dependency Unblock
Kirsten Margarette Lagura — PRJ-010 CSC Agency Implementation
Notes: Need Jessica to provide the mapping information so we can resolve the 72andSunny Dashboards blockers related to periodic budgeting and cost rates.
PROJECT MOVEMENTS
Arriana Pabalate
PRJ-017 Stagwell Global - Skunkworks – Finance Payroll Automation Project [YELLOW]
Progress
As of 3/23, Skunkworks is in execution and planning production deployment next week. The key focus is completing all testing and deployment tasks today to meet the mid-week testing target for go-live. Development and production environments...
Expand
As of 3/23, Skunkworks is in execution and planning production deployment next week. The key focus is completing all testing and deployment tasks today to meet the mid-week testing target for go-live. Development and production environments are already deployed, and configuration tuning was in progress. DNS has been requested, but final naming confirmation may still be pending.
Blocker
Time-critical execution remains the main risk: any incomplete testing or deployment could delay next week’s go-live. DNS naming still requires confirmation. Coordination dependencies (deployment session and shared mailbox setup) may also st...
Expand
Time-critical execution remains the main risk: any incomplete testing or deployment could delay next week’s go-live. DNS naming still requires confirmation. Coordination dependencies (deployment session and shared mailbox setup) may also still pose minor execution risk if not already closed.
Context
This remains a high-priority, time-sensitive initiative with immediate visibility due to the upcoming go-live. At this stage, leadership attention is primarily on confirmation of readiness and whether any last-mile issues could impact launc...
Expand
This remains a high-priority, time-sensitive initiative with immediate visibility due to the upcoming go-live. At this stage, leadership attention is primarily on confirmation of readiness and whether any last-mile issues could impact launch timing.
Casey Younggren
PRJ-010 CSC Agency Implementation [GREEN]
Progress
TEAM: They have their first Stagwell status call on Friday - we are going to go through the Maconomy cleanup deck. Anomaly: Call with their team and Paul tomorrow to discuss the implementation concerns and current timelines. F&B: Coordinati...
Expand
TEAM: They have their first Stagwell status call on Friday - we are going to go through the Maconomy cleanup deck. Anomaly: Call with their team and Paul tomorrow to discuss the implementation concerns and current timelines. F&B: Coordinating with their team - onsite is confirmed for April 28-30. Going to start the Welcome Kit deck this week. INK, Goodstuff, Locaria: Trying to coordinate these to happen in April - need to work with Priya to see pod availability. Allison: Had their Exec Brief yesterday - sent them their homework. Next step is coordinating a secondary briefing (they will have a complicated discovery structure as their organization is so large) Targeted Victory: Still in process of firming up when Welcome Kit / Discovery sessions will take place. They need to be complete with development/UAT stuff by August (they have a hard freeze August - end of the year for election stuff) Next step is to coordinate further with Max. NRG & Redscout: Archie has provided me a warm welcome to the teams - working on dates with their team currently for the Executive Briefings.
Blocker
Risk: INK, Goodstuff, Locaria: pod availability on the Odin side.
Dayne Smith
PRJ-004 Echo [GREEN]
Progress
ttest
Blocker
test
Context
test
Givan Turla
PRJ-006 Movers & Shakers Onboarding [YELLOW]
Progress
Putting this in Yellow just because the go-live is near but the project is on track. Kevin and Damian, got access to Google and setup to M+S Okta is ongoing. We have a session with KAtie today to discuss Slack and pre-stage it for April 1st...
Expand
Putting this in Yellow just because the go-live is near but the project is on track. Kevin and Damian, got access to Google and setup to M+S Okta is ongoing. We have a session with KAtie today to discuss Slack and pre-stage it for April 1st. Plan is to go-live with Google and Slack on Thursday. The rest of the applications can be day 2 items as agreed upon with Lorraine and Katie.
Blocker
No Blockers.
Context
N/A
Kirsten Margarette Lagura
PRJ-010 CSC Agency Implementation [RED]
Progress
For 72andSunny, proxy user creation by Arun is now completed. Milda confirmed during the call that she will complete UAT feedback on the 3 dashboards tomorrow. BizApps team are on standby to resolve issues raised by Milda ASAP if there are,...
Expand
For 72andSunny, proxy user creation by Arun is now completed. Milda confirmed during the call that she will complete UAT feedback on the 3 dashboards tomorrow. BizApps team are on standby to resolve issues raised by Milda ASAP if there are, and promote to Production if none.
Blocker
Still haven't heard back from Jessica on her action items for the blockers.
Context
Timeline cannot be plotted until Jessica provides the mapping information.
Krizzia Vic Amparo
PRJ-010 CSC Agency Implementation [GREEN]
Progress
Doner > Asset Migration (Xinet/Box → AEM): Initial TP has been conducted, and foundational questions around the initiative have been addressed. Doner is in the process of finalizing their assets, while Stagwell is reviewing and analyzing th...
Expand
Doner > Asset Migration (Xinet/Box → AEM): Initial TP has been conducted, and foundational questions around the initiative have been addressed. Doner is in the process of finalizing their assets, while Stagwell is reviewing and analyzing them to identify follow‑up questions and determine the most appropriate migration approach. >Fusion AI–Driven Intake: Initial TP has commenced to establish context for the initiative. Preliminary requirement‑related questions have been addressed. Stagwell is currently reviewing the requirements provided by Doner to assess and define the recommended approach. >Project Boards: Adobe has advised that they are also engaging with Doner on Project Boards related to project management activities. Adobe will coordinate and keep Stagwell informed on upcoming calls to ensure alignment and avoid duplicate efforts across both teams.
Blocker
Asset Migration (Xinet/Box → AEM) - only risk is that Jenn is out next week. Will have to coordinate to other Doner Team members regarding the questions we have for the asset's migration.
Shashankk Shekar Chaturvedi
PRJ-026 Who's Who Revamp [GREEN]
Progress
SSO integration configured with OpenID Connect. First test user (manager) onboarded, resolved activation issue. Project registered in GridOps as PRJ-026. App running with search, recommendations, mentorship, and cross-agency employee discov...
Expand
SSO integration configured with OpenID Connect. First test user (manager) onboarded, resolved activation issue. Project registered in GridOps as PRJ-026. App running with search, recommendations, mentorship, and cross-agency employee discovery features.
Blocker
No blockers at this time.
Context
GCP database migration still in progress. Next steps: DevOps setup and UKG integration post-migration.